The Hydro and Wind Company Securing a clean energy future, profitably

Wind turbine foundations present a challenge at Baulker Farm

Wind turbine foundations present a challenge at Baulker Farm
renewables first - wind turbine foundations for ewt dw54 500 kw turbine

Wind turbine foundations for the EWT DW54 500 kW turbine at Baulker Farm.

The wind turbine foundations have now been completed, but not without a few hitches along the way! In a nutshell, the completed turbine foundations for the planned Powerwind turbine had to be adapted to accommodate an EWT turbine… here’s the story!

Although of fairly standard design, the original Powerwind turbine foundations differed from the norm in that they were slightly narrower and deeper than usual. This was due to the fact that they had to be squeezed in between two large chicken sheds, which somewhat limited the amount of ground surface area available. Nonetheless, the turbine foundations still cover a surface area of approximately 11 x 11 metres.

renewables first - setting the turbine foundations

Assembling the rebar for the wind turbine foundations.

renewables first - setting foundations for ewt turbine

More rebar assembly for the wind turbine foundations.

The photographs (left and right) show the earlier excavations of the Powerwind turbine foundations. The circle of vertical bars visible at the centre of the excavation are the studded rods which bolt to the tower lower flange.  Once the self-levelling grout was poured, this created a dead level flange surface to bolt onto (as shown below left). The picture below right shows the foundation with the formwork removed.

renewables first -

Grouting for the original Powerwind turbine foundations, before they went bust.

renewables first - completed powerwind turbine foundations

Original Powerwind turbine foundations

 

 

 

 

 

 

 

However – having completed the initial foundations for the Powerwind turbine, Powerwind then ceased trading. This meant that the completed Powerwind foundation then had to be adapted to accommodate a different turbine – in this instance, the first DW54 EWT 500 kW turbine that Renewables First has been involved with.

Although by no means a show stopper, this proved to be an expensive problem for the client, as well as an engineering challenge for Renewables First! Although physically the same size turbine, the design details with respect to how the Powerwind and EWT turbines connect to the foundation varies.

Renewables First had to find a way of adapting the Powerwind turbine foundations, in order to accommodate an EWT turbine. Because digging down into the newly constructed concrete foundation was considered too difficult and costly, it was decided to build on top of the existing foundation – essentially laying the EWT foundation on top of the existing Powerwind foundation.

Thus a key engineering task was to successfully link (bond) the new EWT foundation with the Powerwind foundation. This was achieved by lots of drilling and resin-fixing of rebar. The end result was that the level of the reinforced concrete base onto which the foundation cam was embedded, had to be raised by roughly 1.5 metres. The photograph below shows the completed foundation.

Renewables First - turbine foundations for EWT DW54 500 kW turbine

Competed wind turbine foundations for the EWT DW54 500 kW wind turbine.

Want to install a wind turbine?

If you are in the UK then take our Wind Site Self-Assessment - Step 1 of our modular Windpower Feasibility Study. It takes about 20 minutes to work through the basic checks to see if your site might be suitable, including:

  • Estimating wind speed
  • Checking proximity of nearby properties
  • Checking site access and approach roads
  • Investigating connection with the grid

If you are in the Republic of Ireland, or overseas, the first step is to consider our modular Windpower Feasibility Study, so please Contact us to discuss your site further.

Start the process here: Take the Wind Site Self-Assessment