Case Study – Kenningstock Mill Crossflow Turbine on the River Camel, Cornwall

Home » Project Blog » Case Study – Kenningstock Mill Crossflow Turbine on the River Camel, Cornwall
Kenningstock Mill: Crossflow turbine

Kenningstock Mill: Crossflow turbine

Project overview

Crossflow turbine at Kenningstock Mill

Crossflow turbine at Kenningstock Mill

This hydro project involved creating a new split-phase grid connection, the removal of an old Gilkes turbine, refurbishing the turbine house with a lowered concrete floor and installation of a new Crossflow turbine and remote control system.

  • Year: 2015
  • Technology: Crossflow turbine
  • Output: 25 kW
  • Renewables First Role: Feasibility, Design, Project management, Commissioning and ongoing O&M Services
  • Third parties: Ecowave Turbines, John Wood Electrical, Mark Andrews Contracting
  • Spilt-phase grid connection
  • 600 l/s (gross head 6.6 m)
  • Annual energy capture – 107,000 kWh
  • Annual CO2e emissions savings – 54,000 kg

The site

Roof of the turbine house

Roof of the turbine house

The arrangement at Kenningstock Mill was originally designed to provide mechanical power via a waterwheel to process corn and other crops. Over the years, the wheel fell into a state of disrepair and was replaced with a second-hand horizontal axis Francis turbine to provide electricity. The scheme used the existing 750 m long leat and intake structures, which included a rotating drum-screen and a 30 m long cast pipe delivering water across the garden and down through the roof of the turbine house.

A water turbine had been part of the family history at Kenningstock Mill. When confronted with a defunct turbine house, dating back to the 1930’s, complete with antiquated electrics, the new heir approached us to see whether the turbine could be refurbished.

Feasibility work

Our feasibility study showed that a new turbine would be the best option in terms of efficiency and revenue. We contacted Gilkes Ltd, manufacturers of the original turbine (see pictures below), and they kindly provided specification details. This revealed that it was designed for double the head characteristic of the site. This meant that flow through the turbine was reduced by approximately two-thirds, affecting efficiency and therefore limited the output to 10.5 kW.

Original Gilkes turbine

Original Gilkes turbine

Original turbine with connection through the turbine house roof

Original turbine with connection through the turbine house roof

The site characteristics actually suited a crossflow turbine with a mechanical output of 37 kW. However, grid restrictions would limit the electrical output to 25 kW. In addition, the new turbine attracted the Feed-In-Tariff and so improved the revenue five-fold.

Electrical connection

Turbine house control panel

Turbine house control panel

The property was served by one phase of the spilt-phase connection, with the farm next door receiving the other phase. A permit to export of 25 kW (split phase) required a replacement transformer and overhead cable upgrade. Renewables First organised this new service from Western Power Distribution.

The wiring specification within the property was also altered to maximise the use of the power available on the extra phase within the property.

The turbine house

The first task was to remove the old Francis turbine. The draft tube needed to be removed from the concrete floor. Breaking this out was done with extreme caution and fortunately, the underlying ground was suitably cohesive (see picture, below left).

Crossflow turbines are mechanically very simple pieces of equipment with an efficiency of 75 % at the designed flow. However, the new arrangement needed to be connected to the existing penstock coming through the roof of the turbine house and fitted into the room below, so that its draft tube could discharge efficiently into the existing culvert, beside the old Mill building (see diagram, below right).

Digging out the old draft tube

Digging out the old draft tube

Diagram of the new Crossflow turbine

Diagram of the new Crossflow turbine

In order to accommodate the new turbine, the floor of the turbine house needed to be lowered. The team at Renewables First designed a new reinforced concrete floor, which sat on a bed of acoustic insulation in order to prevent any vibration passing through to the Mill building (see picture, below left). This allowed the turbine frame to sit within the floor and receive mechanical equipment using a new lifting beam positioned overhead (below right).
New turbine mounting structure

New turbine mounting structure

Installing the new turbine frame

Installing the new turbine frame

The turbine had to be installed and commissioned in time for Christmas, in order that we could meet an agreed Feed-in-Tariff deadline with Ofgem. This involved assembling mechanical equipment, installing the custom built transition piece to the overhead pipework (below left). Then control panels and electrical units were fitted, and sensors wired before water could be passed through the system (below right).

New Crossflow turbine connecting to overhead pipework

New Crossflow turbine connecting to overhead pipework

Control panels and electrical units

Control panels and electrical units

The leat and intake arrangements

Outside of turbine house, the intake, penstock and culvert to the tailrace were cleaned. Debris was collected before entering the tailrace, to prevent any pollution to the watercourse, and River Camel downstream (see photos below).

Debris removal at the tail race

Debris removal at the tail race

Entrance of tail race at watercourse

Entrance of tail race at watercourse

The turbine was successfully commissioned in December 2015, and involved the collaboration of 5 companies, all based in the South West. The calculated annual energy capture of the turbine is 107,454 kWh per year. This is enough to power 26 UK homes and will lead to an annual CO2e emissions saving of 53,727 kg.

Aware of the strong local energy market in Cornwall, the Client was advised about a peer-to-peer energy matching platform for renewables. Kenningstock Mill was matched with a portal supporting the Eden Project, who are keen to procure as much local power as possible, because they had an interest in rounding off their energy mix and hydro provides more of a baseload profile.

Customer Testimonial

“Having taken over my aunt’s converted watermill in Cornwall in 2011, we inherited what must have been one of the first hydro schemes installed in the South-West. The first decision we had to make was whether to update the existing scheme, based around a reconditioned Francis turbine installed in the 1970s, or replace it with a more efficient modern turbine.

We commissioned Renewables First to carry out a feasibility study and the results were not unexpected. An updated Francis turbine, even with the river in flood, would only ever operate at 50% of capacity because of the limitations of the site. Guided by them, we took the decision to install a new 25 kW Cross-flow turbine made in the South-West by Ecowave.
We tasked the Renewables First team with using as much of the existing infrastructure as possible while keeping civil engineering work to a minimum – not an easy job given the restricted nature of the site.

The result was a resounding success. The technical skills shown by the team and their dedication to delivering the scheme on time and to the highest possible standards was outstanding.”

“In the spring of 2016 we reached a decision that the pre-existing screen used to prevent leaves, wood and fish from passing through the turbine, was no longer fit for purpose. We had no hesitation in asking Renewables First’s sister company, GoFlo, to design and build a new automated filter screen to sit in the leat across the entrance of the penstock. This was installed in the autumn. After a few minor adjustments, we now have a modern hydro scheme, capable of operating in all conditions, throughout the year.

We would have no hesitation in recommending Renewables First to anyone contemplating the installation of a small-scale, hydro-electric scheme.”

Robert Rice,
Kenningstock Mill,
Advent,
Cornwall.

For more information about the installed GoFlo screen at Kenningstock Mill, go here:
https://www.gofloscreens.co.uk/goflo/case-study-kenningstock-hydropower-system-with-goflo-travelling-screen/