The Hydro and Wind Company Securing a clean energy future, profitably

Renewables First to install Hibaldstow wind turbine

Renewables First to install Hibaldstow wind turbine
Hibaldstow wind turbine

Renewables First: installing the Hibaldstow wind turbine.

With the turbine foundations and all electrical components in place, the Hibaldstow wind turbine installation was able to commence – despite the lousy weather!

The image on the left shows the lower tower section being lifted toward the turbine foundations. Two cranes are visible; the main crane is lifting the upper end of the tower section, with the smaller crane acting to temporarily prevent the lower end from swinging or colliding with other objects on site. Once sufficient height is attained, the main crane takes full control of the lifting procedure.

The centre and right images show the upper tower section being lifted; at first with two cranes, but then with the main crane only as the upper tower section is lowered onto the lower tower section. Once installed, the turbine tower stands 50 metres above the foundations below.

Renewables First - wind turbine installation

Wind turbine installation: lifting the upper tower section.

Renewables First - Hibaldstow wind turbine

Wind turbine installation: ; lifting lower tower section.

Renewables First - Hibaldstow wind turbine

Wind turbine installation: lowering upper tower section into place.

Once the tower was in place, the next step was to install the nacelle. The twilight image below (left) shows the nacelle being lifted into position on top of the upper tower section. The nacelle will enable the rotor blades to be turned into the prevailing wind, maximising the efficiency of the turbine.

The following day the generator and rotor blades were fitted. The image below (right) shows the 30-tonne generator being lifted into position. This will be fixed to the nacelle perched on top of the upper tower section 50 metres above the ground.

Renewables First - Hibaldstow wind turbine

Lowering the nacelle into position.

renewables first - Hibaldstow wind turbine

Lifting the generator for the Hibaldstow wind turbine.

 

 

 

 

 

 

 

With the generator in place the pre-assembled hub and rotor blades were attached, completing the installation. The EWT 500 kW turbine has a rotor diameter of 54 metres and a hub height of 50 metres. It is calculated that the Hibaldstow wind turbine will provide at least a large proportion of, or even match the on-site demand for electricity. This will significantly reduce running costs and improve the environmental sustainability of the enterprise.

renewables first - Hibaldstow wind turbine

Completed wind turbine iustallation.

 

 

 

 

 

 

 

 

renewables first - ewt dw54 500 kw turbine

Renewables First – Wind turbine installation at Hibaldstow Farm.

 

 

Want to install a wind turbine?

If you are in the UK then take our Wind Site Self-Assessment - Step 1 of our modular Windpower Feasibility Study. It takes about 20 minutes to work through the basic checks to see if your site might be suitable, including:

  • Estimating wind speed
  • Checking proximity of nearby properties
  • Checking site access and approach roads
  • Investigating connection with the grid

If you are in the Republic of Ireland, or overseas, the first step is to consider our modular Windpower Feasibility Study, so please Contact us to discuss your site further.

Start the process here: Take the Wind Site Self-Assessment