Constructing the underground hydro turbine house

Home » Project Blog » Hydropower Projects » Constructing the underground hydro turbine house
Renewables First - Saddleworth Community Hydro turbine house construction

Renewables First – Constructing ground level loading bay of hydro turbine house

The Dovestone hydro turbine house structure is now well underway. Designed by Renewables First, the hydro turbine house will be a triple-layered construction, with each layer serving a specific function. Most of the turbine house will be below ground level, and this is currently where all activity is focused.

Saddleworth Community Hydro turbine house construction

Turbine house basement floor construction.

So how will it look? At ground level there will be a loading platform only (the construction of which can be seen in the main picture above) and an access stairway down to the turbine chamber.

Going down yet another level to beneath the turbine chamber, the turbine house sump and culvert (connecting the sump and stilling basin) will be located.

 

 

Saddleworth Community Hydro turbine house construction

Hydro turbine house construction

The construction of the hydro turbine house forms a major part of the project works. Once completed, the mechanical and electrical components of the scheme can be installed. This will initially include the Crossflow turbine, generator and the penstock connection, but soon after followed by the electrical, control and telemetry equipment.