Windpower Projects

Home » Project Blog » Windpower Projects
Wind turbine commissioning at Blacktoft Nursery

Wind turbine commissioning at Blacktoft Nursery

With the wind turbine commissioning complete, the turbine was officially handed over to Blacktoft Nursery. Four months later in spring sunshine, we returned to the site and took a selection of photographs of the 500 kW wind turbine in operation.

read more
Blacktoft Nursery wind turbine

Blacktoft Nursery wind turbine

The 500 kW wind turbine at Blacktoft Nursery could generate 1,726,095 kWh of electricity per year, which is equivalent to the amount of electricity used annually by 405 average households.

read more
EWT DW54 500 kW turbine for Hibaldstow Farm

EWT DW54 500 kW turbine for Hibaldstow Farm

Given their experience and technical expertise, Renewables First were hired to specify and design the scheme, as well as project manage the civil, mechanical and electrical components of the project. The sequence of pictures below illustrate some of the key activities in the run up to installing the EWT 500 kW turbine.

read more

Older Project Posts -
Windpower Projects

Baulker Farm wind turbine running

The newly installed EWT 500 kW wind turbine at Baulker Farm is performing to expectation and makes the site almost self sufficient in electricity. Renewables First has project managed the design and installation of the scheme from the instant the client obtained planning permission.

EWT DW54 wind turbine from the inside

Once the Baulker Farm wind turbine was installed, the commissioning and handover day provided an opportunity to ascend the turbine tower to the hub, in order to check everything is as it should be – as well as provide an opportunity to take some pictures!

Baulker Farm wind turbine blades connected to the hub

When assembling the hub and wind turbine blades, the challenge at Baulker Farm was one of space limitations due to the proximity of farm buildings and the large chicken sheds. With the rotor blade diameter of the EWT 500 kW turbine being 54 metres, a large surface area was required.

Wind turbine generator lifted into place

The turbine generator is first lifted from its horizontal position on the delivery vehicle into a vertical position, ready for it to be fixed to the nacelle at the top of the turbine tower.

Wind turbine tower sections connected at Baulker Farm

With the lower tower section in place, the next phase of the wind turbine installation involves the upper tower section being installed. As with the lower section, both the main and tail cranes were used for the initial lifting until the section was vertical, at which point the main crane took over.

Installing the lower wind turbine tower section

With the turbine foundations completed, the site was ready for the DW54 EWT 500 kW turbine to be installed. The first to arrive was the lifting crane. This was a 1000 tonne mobile crane, required to lift the huge 30 tonne tower sections and generator up and over the chicken shed!

Baulker Farm wind turbine earthing solution

The site at baulker farm is also interesting in that there were challenges with the wind turbine earthing. This is because the ground is comprised mostly of sand which has a very low conductivity.

Wind turbine foundations present a challenge at Baulker Farm

Having completed the initial foundations for the Powerwind turbine, Powerwind then ceased trading. This meant that the completed Powerwind foundation then had to be adapted to accommodate a different turbine – in this instance, Renewables First specified a DW54 EWT 500 kW turbine.

Are you considering a low carbon renewable energy project?

Renewables First have considerable experience and full project capability, from initial feasibility studies through to system design and installation for Hydro, Wind, PV, Energy Storage Systems, Water and Ground Source Heat Pump Systems.

We also specialise in consultancy for Energy independence / Back-up electricity systems, Net zero energy production, Off-grid / Standalone and Remote power systems

Please contact us about your low carbon energy project today.