The Hydro and Wind Company Securing a clean energy future, profitably

Wind turbine commissioning at Blacktoft

Wind turbine commissioning at Blacktoft
Renewables First - wind turbine commissioning

Renewables First: Wind turbine commissioning at Blacktoft Nursery.

Following the turbine installation in November, December 2014 saw the final technical stages completed: energisation and wind turbine commissioning.  These are the final checks before the system can be handed over to the client.

Energisation is the technical process by which the turbine is connected to the local electricity grid network. This means that the nursery can then both import electricity from the grid (when demand exceeds supply from the turbine), as well export (and sell)  electricity to the grid when output from the turbine exceeds demand from the nursery. Wind turbine commissioning involves a series of technical checks to ensure that the system is performing properly.

Now that the turbine is fully operational and grid connected, it can fulfil its role as a generator of electricity from a renewable and abundant resource – the wind.

The Blacktoft Nursery project is now entering the final stages of development. This will focus mainly on landscaping, restoration and making good of the site.

Several months on…

Below is a selection of images taken in early spring, four months later.

Approaching…

Renewables First - Blacktoft Nursery wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

Getting closer…

Renewables First - Wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

Renewables First - Wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

From the base looking up…

Renewables First - Wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

Renewables First - Wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

Looking around…

Renewables First - Wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

Renewables First - Wind turbine commissioning

Blacktoft Nursery EWT 500 kW wind turbine

Wind turbine commissioning - Renewables First

Blacktoft Nursery EWT 500 kW wind turbine

Wind turbine commissioning - Renewables First

Blacktoft Nursery EWT 500 kW wind turbine

Want to install a wind turbine?

If you are in the UK then take our Free Wind Site Self-Assessment - Step 1 of our modular Windpower Feasibility Study. It takes about 20 minutes to work through the basic checks to see if your site might be suitable, including:

  • Estimating wind speed
  • Checking proximity of nearby properties
  • Checking site access and approach roads
  • Investigating connection with the grid

If you are in the Republic of Ireland, or overseas, the first step is to consider our modular Windpower Feasibility Study, so please contact us to discuss your site further.

Start the process here: Take the Wind Site Self-Assessment

Already completed the Wind Site Self-Assessment?

Enter your access code here to see the next available module(s):

Alternatively, contact us to talk about a windpower project.