Baulker Farm wind turbine blades connected to the hub

Baulker Farm wind turbine blades connected to the hub

When assembling the hub and wind turbine blades, the challenge at Baulker Farm was one of space limitations due to the proximity of farm buildings and the large chicken sheds. With the rotor blade diameter of the EWT 500 kW turbine being 54 metres, a large surface area was required.

Read more...

Wind turbine tower sections connected at Baulker Farm

Wind turbine tower sections connected at Baulker Farm

With the lower tower section in place, the next phase of the wind turbine installation involves the upper tower section being installed. As with the lower section, both the main and tail cranes were used for the initial lifting until the section was vertical, at which point the main crane took over.

Read more...

Installing the lower wind turbine tower section

Installing the lower wind turbine tower section

With the turbine foundations completed, the site was ready for the DW54 EWT 500 kW turbine to be installed. The first to arrive was the lifting crane. This was a 1000 tonne mobile crane, required to lift the huge 30 tonne tower sections and generator up and over the chicken shed!

Read more...

Wind turbine foundations present a challenge at Baulker Farm

Wind turbine foundations present a challenge at Baulker Farm

Having completed the initial foundations for the Powerwind turbine, Powerwind then ceased trading. This meant that the completed Powerwind foundation then had to be adapted to accommodate a different turbine – in this instance, Renewables First specified a DW54 EWT 500 kW turbine.

Read more...

Case study: Rochdale hydropower Archimedes screw turbine

Case study: Rochdale hydropower Archimedes screw turbine

The Rochdale hydro scheme helps to power Rochdale’s £11.5 million Transport Interchange, linking bus and rail services for Rochdale and the surrounding area. It is reputed to the first Interchange in Europe to run partly on hydro-electric power, thanks to the 21 kW Archimedes screw turbine harnessing power from the River Roch.

Read more...

Case Study – Micro hydro Archimedes Screw turbine at Tipton Mill

Case Study – Micro hydro Archimedes Screw turbine at Tipton Mill

The Tipton Roller Mill hydro scheme comprises a 28 kW grid connected Archimedes screw turbine. The scheme is located between Tipton Weir and the Roller Mill. The turbine is housed in a newly constructed channel between the existing leat and the River Otter. The turbine will churn up to 1500 litres water per second over a 2.6m head.

Read more...