Hydropower Site Assessment
& Design

Home » Services » Hydropower » Hydropower Learning Centre » Hydropower Site Assessment & Design

Written by: Phil Davis, Managing Director at Renewables First. Phil has been working in the renewables sector since 2001 and is a recognised expert in hydropower as well as wind and solar PV at all project stages.
Reviewed by the Renewables First engineering team for technical accuracy.

Reviewed June 2026

Successful hydropower projects depend on careful site assessment, good system design and a clear understanding of environmental and practical constraints.

This learning page covers the key considerations involved in developing and operating small and micro hydropower schemes, from site suitability and system layout to environmental impacts and long-term performance.

Frequently Asked Questions

What makes a good hydropower site?

A good hydro site is a valuable asset
You could write a book what makes a good hydro site, but in summary:

  • Good head
  • Good flow
  • Simple site layout with main parts close together
  • Good grid connection
  • Good site access
  • Single ownership of the site, or cooperative neighbours
  • Not too many environmental sensitivities

Good head

In our hydropower projects, head is typically the most important factor in having a good hydro site, provided all of the other parameters are satisfactory. The power, and therefore energy output from a site is proportional to head. The cost of a hydro system is to a large degree determined by the physical size of the civil engineering structures and the turbine, so as heads get lower and water volumes increase (because the pressure and therefore velocities decrease), the system gets more expensive. The opposite is true as the head increases; the system gets physically smaller and costs less while at the same time the power and energy production increases, making the return on investment higher. This doesn’t mean that low head sites are bad – at the end of the day the head you have is what you have – but it does mean that all things been equal, higher head sites are better than lower head sites. It also means that for any site it is always worth doing whatever you can to increase the head and reduce head losses, which can all be done by good hydropower design.

Good flow

You can’t do anything without sufficient flow, so this is also important. Generally speaking, low head sites tend to have higher flow rates because they are in the lower-end of a river’s catchment in lowland areas, and therefore have a large catchment upstream with lots of tributaries. Higher head sites are usually higher in the catchment where the land is steeper (hence the higher heads possible), but also the catchment is smaller, so flow rates tend to be less.

This is no ‘right’ flow rate, it is just a matter of calculating how much energy you can generate and deciding whether it will be economically viable.

Simple site layout with main parts close together

This is mainly in relation to construction and installation works. The perfect site from a construction perspective is a green field, with no constraints. As complications arise such as historic structures, public rights of way, historic machinery and natural features (like cliffs, bed-rock, waterfalls, springs etc.) the project gets more complicated and therefore expensive. Very few projects are ‘perfect green field sites’, so don’t worry if you have some of the constraints listed above, but be aware that more constraints means more construction cost.

It is also beneficial if the intake, turbine location and discharge are all reasonably close together. On lower-head sites this ensures that the civil engineering (i.e. concrete) structures are relatively small, hence lower cost. On higher-head system it means the penstock-pipe is reasonably short, which is important because this is often the most expensive part of a high-head hydropower system.

Good grid connection

You may have a cracking hydropower site, but it is no good if you can’t sell the power because there is no grid connection! You not only need a physical grid connection, but it also needs to be ‘strong’ enough to take all of the power you will generate. Generally you will need a three-phase 11,000 volt supply either on-site or nearby. Ideally you would already have a suitable on-site transformer or substation so you can connect on the low-voltage (LV) side.

Very small systems (<25 kW) may be able to connect to a single-phase supply, and in some cases you can connect up to around 80 kW using a special ‘split-phase’ transformer.

It isn’t possible to tell how ‘strong’ a three-phase 11 kV supply is without formally asking the Distribution Network Operator (DNO). Renewables First can make grid connections applications on your behalf and obtain quotes for any grid upgrade works required. See here for more details.

Good site access

For the construction stage, and to a lesser degree for on-going maintenance, the site will need access for construction equipment, delivery vehicles, and for large systems, cranes. Hence narrow lanes, tight corners, soft ground and obstructions caused by buildings can all cause problems which in the worst case would prevent the project progressing, and in the best case may just mean additional cost. These issues would all be considered when the hydro feasibility study was carried out.

Single ownership of the site, or cooperative neighbours

In a perfect world the entire site would be owned by a single landowner. This not only makes the environmental consenting easier, but also means that commercial agreements between landowners are not required, which if they are usually means sharing a percentage the revenue. It is surprising how often such commercial agreements cannot be concluded because of irrational greed from one party, so it is well-worth discussing the project and how all stakeholders would be compensated at an early stage and getting the appropriate legal agreements signed before proceeding with the expensive consenting and design stages.

Not too many environmental sensitivities

As discussed in more detail on the consenting pages, the process of getting environmental consents from the Environment Agency in England and Wales is bureaucratic and slow, though it is slightly better under SEPA in Scotland.

In all regions the more ecologically-sensitive a site is, the longer and more expensive the consenting process will be. In general terms hydropower systems can be safely incorporated into all but the most sensitive environments, and will always be designed to have no negative impact, and will often provide a net improvement, particularly for fish passage.

So environmental sensitivities (like migratory fish, fish spawning, protected species etc.) are not show-stoppers, but do slow the consenting process down and make it more expensive.

What are the main hydropower project risks?

The following hydropower project risks could all affect the viability of a hydropower project. Most of the risks can be significantly reduced by developing your project with an experienced hydropower designer / installer, such as Renewables First.

Consenting and outline design stage

  • It is important to have written agreements in place if multiple-landowners are involved before any substantial work is completed.
  • There is always a risk that the environmental regulator may not issue the required licences and consents, though this can be mitigated by good quality feasibility and pre-application work.
  • Securing a grid connection can be a risk, particularly in remote locations, so permission to grid connect should be obtained at the outline design stage.
  • Planning consent can be a risk, but is not normally an issue provided the system is well designed.

Detailed design/construction stage

  • There is a risk that the ground conditions for foundations are not as good as anticipated, though this can be mitigated by reference to geotechnical survey data and on-site geotechnical analysis.
  • Construction works are normally conducted during the drier parts of the year, but there is always a risk that severe wet weather will occur which can cause damage at the site and delay works.

Operational stage

  • Regulatory licenses must be renewed every 12 years. There is a presumption of renewal, but if any new environmental legislation has come into force it is possible that the hydro system will need upgrading to meet the new requirements, at additional cost.
  • The Feed-in Tariff is a Government scheme that could be subject to change, though recent legal challenges to changes have been won by the generators, which adds some confidence. The Feed-in tariff for new renewable energy projects was scrapped in April 2019.
  • The annual energy prediction from the hydro system is based on long-term average flows, but year-to-year flows can vary significantly about this average: this can be very beneficial if you have a series of wetter years, but it can go the other way as well and have several dryer years.
  • The export price for electricity can go up as well as down, though the general consensus is that energy prices will continue to rise at above-inflation rates for the foreseeable future.

What is the minimum head and flow I need?

Firstly you always want as much head as possible, and more is always better. Assuming you’ve maximised the head you then need enough flow to make it economically viable, then more is always better due to the economies of scale from building larger systems. It is the combination of minimum head and flow that determine the power output.

The following table gives indicative minimums – but remember more is always better. The table shows the minimum annual mean (i.e. average) flow rate required for a given head to generate a maximum power output of 25 kW, which as discussed here is considered the smallest economically viable hydropower system. Any more flow for the same head will generate more power, and there is no upper limit.

minimum head and flow

minimum head and flow

See here for more information on how to calculate the power output from the head and flow available at your site.

Can I use hydro power off-grid and be independent?

Yes, but it is generally prohibitively expensive and not worth the extra complexity. Using hydro off-grid means that you need more expensive types of equipment / generator and much more complex control systems, and a means of storing energy (or dumping it) becuase the overall electrical system must be balanced.

In the UK we are very fortunate in having one of the best electricity distribution networks in the world. Most people only have one or two power cuts a year, and even these are often of short duration or during the night when it doesn’t really matter. Because our distribution network is so reliable, it is much simpler technically and much more cost effective to be grid connected, and effectively use the grid as a giant battery to dump surplus energy to and draw energy from as required – however if power to the grid fails the the hydro power system will shut down.

If you really want to use hydro off-grid then we can design and supply a suitable system, but as a ballpark estimate assume it will add 25% to the project cost, and the resulting system will be more complex and require more maintenance.

Can I consume hydropower energy on site?

Yes, you can consume energy on site, provided that the wind turbine can connect into the site distribution board. Sometimes this is not possible because the wind turbine site is geographically separate from the site distribution board, or the cable run would be excessively long.

Whenever possible the preferred option would be to connect into the site distribution board because this allows you to offset imported energy which significantly increases the income from the wind turbine.

It is important to remember that electricity flows like water and will always follow the easiest route to the nearest load; this means that all of the site owner’s loads (i.e. lighting, sockets, machinery, air conditioners etc.) that connect to the same distribution board would be supplied firstly by the wind turbine, and only once all of these loads had been satisfied would any surplus energy from the wind turbine flow backwards through the incoming supply cables, either to the next nearest distribution board on the site, or out through the export meter to the grid.

Also, because the electricity produced by the wind turbine is fully grid-synchronised, it will mix seamlessly with grid-imported electricity. This means that if the wind turbine cannot supply all of the site’s loads, then all of the electricity from the wind turbine would go towards the loads and any deficit would be seamlessly imported from the grid.

Equally, if the wind turbine was supplying all of the local loads but then a reduction in the wind speed caused the output to suddenly drop, then the grid would instantly supply more to make up the deficit. From a consumers point of view the source of the electricity would be unknown; it could be from the wind turbine, the grid or a combination of both.

In the situation where the on-site loads far exceed what the wind turbine could ever produce, then all of the electricity generated by the wind turbine would be consumed on site. For example, if a wind turbine with a maximum power output of 500 kW was connected to a site that had a baseload (i.e. the minimum load 24/7) of 1 MW, then 100% of the energy generated by the wind turbine would be consumed on site.

Financially this would be a good arrangement because the price paid for importing electricity from the grid is typically 12 p/kWh (varies between 8 – 16 p/kWh depending on the import tariff), so if the amount of import could be reduced, for every kWh it was reduced by the site owner would save 12 p. If you compare this saving of 12 p/kWh to an export price of 6.5 p/kWh, you can see that offsetting on-site loads is worth almost double the value of exporting the electricity.

If it isn’t physically possible to connect to the onsite distribution board because the cable length would be too long, or the generation system is significantly larger than the onsite loads, or there simply isn’t an on-site distribution board, then the system would be directly connected to the grid via a dedicated grid connection.

Can I generate hydropower using an old water mill?

Old watermills were the keystone of power generation a few centuries ago, and in most cases the hydro resource at a watermill site will be unchanged, so yes you should be able to generate using an old water mill.

The key question is whether it will be possible to install a modern hydro system and make a reasonable return on investment. A lot of watermill sites are small corn mills, and in many cases the cost of a modern hydro system will be prohibitive. Larger mills may have the potential for larger systems (>25 kW) which could make economic sense, and larger industrial sites of 100 kW+ can make very good modern hydro sites.

It is worth mentioning that generally, small sites that used to have mill ponds are often not suitable for modern hydro systems. The issue is that small sites with millponds have them because the river feeding them did not have enough flow to power a mill by itself, so the water had to be saved-up and the mill operated for a few hours when the pond was full. Nowadays the environmental regulator would not allow a site to store then release water like was done in the olden days, so these sites generally don’t have enough flow in the river for a modern system. Larger sites with mill ponds may still work, so it is always worth calling our office to check.

Generally speaking a modern hydropower system can be installed sympathetically into a historic water mill, and we have installed lots of systems into listed buildings with no problems. All of the same turbine options would be available for old watermills as would be suitable for a green-field site, and for smaller systems it is often worth considering a new ‘modern’ waterwheel which can have a reasonable efficiency and can look suburb in a historical setting.

As with all hydropower sites, the process starts with a hydro feasibility study to look at the site in detail and work out what would be possible.

How do you connect hydro power to the grid?

Without going into the highly complex electrical engineering behind this, there are two basic ways to connect hydro to the grid: using a fixed-speed induction generator or via a grid-tied inverter.

Fixed-speed induction generator

This is the most common method for grid connecting hydropower systems and is generally used for all turbine types except Archimedean Screws, which can use this method but can also benefit from using a grid-tied inverter because this allows variable-speed operation.

A fixed-speed induction generator is essentially identical to an induction motor, only it spins at above synchronous speed because it is being pushed around by the turbine, rather than pushing a load around.

An induction generator is grid-excited, which means that the magnetic field that must be created by the generator’s stator windings is energised by the grid. This has the advantage that by default the electricity generated must be perfectly grid-synchronised because the grid is providing the excitation. However, this does mean that if there is a power cut the excitation ceases and the generator stops working, so during a power cut the hydro system will shut down.

Grid-tied inverter

An inverter is a power-electronic device that can convert DC electricity into AC. In hydropower applications two inverters are actually used in this format:

Generator > inverter-rectifier > inverter > grid

This essentially makes the generator independent of the grid. The inverter connected to the grid is ‘tied’ to the grid, which effectively means it is excited by the grid in a similar way to a fixed-speed induction generator (albeit using power electronics and a control system). The inverter connected to the generator is controlled by the system controller which allows it to operate over a range of voltages and frequencies, and by doing this the generator will spin over a range of speeds – hence is ‘variable speed’. Although this means that the electricity generated by the generator will be at variable-voltage and frequency which is completely incompatible with the grid, this doesn’t matter because the rectifier in-between rectifies the ‘dirty AC’ from the generator to smooth DC, and then the grid-tied inverter produces perfect grid-synchronised AC electricity.

Sequence of events to connect hydro power to the grid

The following sequence applies broadly to fixed and variable-speed hydropower systems:

  • Water inlet to hydro system slowly opens, turbine starts to rotate.
  • As flow rate through the turbine increases the generator begins to excite and produce AC electricity, but at a lower voltage and frequency than the grid can accept.
  • The control system monitors the voltage and frequency, and adjusts to flow rate through the turbine to make it the same as the grid.
  • Once within specification, the electricity waveforms of the generator and grid must by synchronised so that they are ‘in phase’; this is done by either adjusting the flow rate by a tiny amount and waiting, for by diverting a small amount of generated energy to a dump load.
  • Once synchronised, a ‘contactor’ is closed (automatically) that directly connects the generator (or grid-tied inverter) to the grid – it is now ‘grid connected’.

From this point forward the hydro system is controlled by the flow available in the river and will generate as much power as possible from the available flow.

Obviously this is quite a simplistic explanation, but the process is clear. From a technical point of view a variable-speed system operates in a slightly different way, but the principle is the same.

Which hydro turbine types do Renewables First supply?

Renewables First are proudly independent of hydro turbine suppliers and will always recommend the most appropriate turbine from reputable, good quality manufacturers so what we  only specify good quality equipment that has a history of reliable continuous operation to ensure that your project achieves a maximum return on investment. There are a number of hydro turbine types from a variety of suppliers.

As part of your project we can supply any of the main hydro turbine types including the following, the type will be determined by your site characteristics:

Is there a hydropower association for people interested/involved in hydropower?

Yes. The British Hydropower Association is the trade association for the UK hydropower industry and it represents hydro consultants, developers, site owners, hardware suppliers and other interested parties of all sizes.

The BHA does valuable work in promoting hydropower and in discussing various issues with government departments and regulators so that hydro is protected from inappropriate legislation, is better understood and is widely recognised as a reliable and valuable source of renewable energy.

Renewables First are Company Members of the British Hydropower Association and strongly support their work.

Are you considering a hydropower project ?

Renewables First have considerable experience as a hydro consultant and have a full project capability, from initial feasibility study through to system design and installation.

The first step to develop any hydropower site is to conduct a full feasibility study.
Contact us about a feasibility study today!

Once complete, you will understand the site potential and be guided through the next steps to develop your project. You can read more about hydropower in our Hydro Learning Centre.

Minimise manual cleaning of your intake screen, maximise the financial return of you hydropower system and protect fish and eels, with GoFlo Travelling Screens. Find out more here.