We offer a free-of-charge initial assessment for all heat pump projects, to provide details of the expected performance and project finances.
After that, we will carry out a site survey to review the heating demand, emitter specifications and suitability of the watercourse.
Smaller projects (<100kW) typically take 4-5 months, including:
1. Site survey and EN12831 heat loss calculations
2. Detailed design (+ consenting if required)
3. Installation & commissioning
Larger projects (>100kW) typically take 7-9 months, including:
1. Site survey
2. Feasibility study
3. Detailed design & consenting
4. Installation & commissioning
Renewables First offers a ‘turnkey’ solution from start to finish. Our scope includes the heat pump, heat collectors, and the pipework between the two. We will advise your heating engineer to ensure that the internal heating and hot water systems work seamlessly with the heat pump.
Are you considering a water-source or ground-source heat pump project ?
Renewables First have considerable experience and full project capability, from initial feasibility study through to system design and installation.
The first step towards a water-source or ground-source heat pump project is tell us about your project. The best way of doing this is via our tailored online Enquiry Form.
Once complete, one of our engineers will evaluate the site potential before contacting you to discuss the next stage of your project.
Learn more about Heat Pump projects at our Heat Pump Learning Centre.